Ground mounted solar installation

Connecting commercial solar panels to the UK electricity grid requires formal approval from your local Distribution Network Operator (DNO). This regulatory process ensures grid safety and stability while enabling businesses to generate clean energy and potentially export surplus power back to the grid.

Understanding DNO requirements early in your solar project planning can prevent costly delays and ensure your installation meets all technical standards. This guide covers everything you need to know about the commercial solar DNO application process in the UK.

When You Need DNO Approval for Commercial Solar

DNO approval is required for all grid-connected commercial solar installations, regardless of size. The approval ensures your system won't adversely affect the local electricity network or other customers' power supply.

You'll need DNO consent for:

  • New commercial solar installations connecting to the grid
  • Existing installations being expanded or modified
  • Systems with battery storage that can export power
  • Any generation equipment that may operate in parallel with the public network

The application process must be completed before your installation can be commissioned and connected. Installing without proper DNO approval can result in disconnection and potential legal issues.

Export vs Non-Export Systems

Even if you plan a non-export system that only supplies your own premises, you'll still need DNO notification. Grid-tied inverters can potentially export power during low consumption periods, so DNOs must assess all connections for safety compliance.

G59 vs G99 Application Requirements

The type of DNO application required depends on your installation's capacity and connection voltage level.

G99 Applications

G99 is the current engineering recommendation covering most commercial solar installations. It applies to:

  • Single-phase connections up to 16A per phase
  • Three-phase connections from 16A to 75A per phase
  • Systems typically ranging from small commercial to several hundred kilowatts

G99 applications require detailed technical documentation and can involve witness testing of protection equipment.

G59 Legacy Applications

G59 was the previous standard, now largely superseded by G99. Some existing installations may still operate under G59 approvals, but new applications typically follow G99 requirements.

The transition to G99 introduced more stringent technical requirements, particularly around fault ride-through capabilities and power quality monitoring.

DNO Application Process Step-by-Step

The DNO application process involves several stages, each with specific requirements and timelines.

Stage 1: Initial Enquiry

Submit basic project details to your local DNO, including:

  • Site location and connection point
  • Proposed generation capacity
  • Expected commissioning date
  • Basic single-line diagram

The DNO will provide initial feedback on network capacity and connection feasibility.

Stage 2: Formal Application

Submit your complete application package with all required technical documentation. This triggers the formal assessment process and associated fees.

Stage 3: Technical Assessment

The DNO reviews your application against network capacity, safety standards, and technical requirements. They may request additional information or design modifications.

Stage 4: Connection Agreement

Once approved, you'll receive a connection agreement outlining terms, conditions, and any ongoing requirements for your installation.

Required Technical Documentation

DNO applications require comprehensive technical documentation demonstrating your system's compliance with grid connection standards.

Essential Documents

  • Single-line electrical diagram: Showing your complete installation from solar panels to grid connection point
  • Protection settings: Detailed inverter and protection relay configurations
  • Equipment specifications: Technical datasheets for inverters, transformers, and protection devices
  • Site layout plans: Showing equipment locations and cable routes
  • Earthing and bonding arrangements: Demonstrating electrical safety compliance

G99 Specific Requirements

G99 applications additionally require:

  • Power quality impact assessments
  • Fault level calculations
  • Evidence of equipment type testing
  • Commissioning and witness test procedures

Your qualified commercial solar installer should prepare all technical documentation as part of their service, ensuring accuracy and compliance with current standards.

Application Timelines and Costs

DNO application timelines vary depending on system size, network complexity, and current application volumes.

Typical Timelines

  • Small commercial systems (up to 50kW): 4-8 weeks for straightforward applications
  • Medium commercial systems (50-200kW): 8-12 weeks including technical assessments
  • Large commercial systems (200kW+): 12-20 weeks for complex network impact studies

Application Costs

DNO fees typically include:

  • Application processing fees (usually £100-500 depending on capacity)
  • Connection charges for any required network modifications
  • Ongoing use of system charges for larger installations

Some installations may require network reinforcement, significantly increasing connection costs. Early engagement with your DNO helps identify potential additional charges.

Common DNO Application Mistakes to Avoid

Several common mistakes can delay your DNO approval or result in application rejection.

Incomplete Technical Documentation

Submitting incomplete or inaccurate technical information is the most frequent cause of delays. Ensure all protection settings, equipment specifications, and electrical diagrams are complete and consistent.

Incorrect Connection Point Selection

Choosing an inappropriate connection point can impact costs and approval times. Your installer should assess multiple connection options during initial design phases.

Inadequate Protection Settings

Incorrectly configured protection equipment can cause application rejection. Protection settings must comply with G99 requirements and coordinate with network protection schemes.

Missing Equipment Certifications

All electrical equipment must meet relevant UK standards and include appropriate certification documentation. Missing certificates can halt the approval process.

Late Application Submission

Submitting your DNO application too late in the project timeline can delay commissioning and impact your business case. Plan for DNO approval early in your project schedule.

Working with Experienced Installers

The DNO application process requires specialist knowledge of grid connection standards, electrical protection systems, and regulatory requirements. Qualified commercial solar installers handle these complex applications as standard practice, ensuring accuracy and minimising delays.

An experienced installer will coordinate the entire DNO approval process, from initial enquiry through to final connection agreement, allowing you to focus on your business while ensuring regulatory compliance.

Ready to explore commercial solar for your business? Nu.energy connects you with qualified commercial solar installers who handle all aspects of DNO applications, ensuring smooth project delivery from initial consultation through to grid connection and commissioning.

References

  1. Energy Networks Association — G99 Grid Code
  2. Ofgem — Electricity Distribution
  3. Solar Energy UK — Commercial Solar Guide
Last updated: 03 May 2026